Public works · City of Minneola

Oak Valley Boulevard traffic calming

Council selected temporary speed humps before later repaving. Subsequent minutes report speed tables installed and describe feedback from the pilot.

Traffic calming installed (Aug 2025); work status unknown

Evidence as of

  1. Planned

    Source: March 4, 2025 City Council minutes, p. 3

  2. FundedNot yet on record
  3. Traffic calming installed (Aug 2025); work status unknownDocumented; date not on record

    Source: August 5, 2025 City Council minutes, p. 2

  4. CompleteNot yet on record

Staff reported speed tables installed at the Aug 5, 2025 meeting (start date not on record); full project completion and later repaving are unverified. Funding and verified completion: Not yet on record.

What has happened

  1. Council consensus: humps first, repaving later

    The minutes record consensus for temporary rubber bolt-on speed humps, with advanced signage and striping discussed.

    Source: March 4, 2025 City Council minutes, PDF page 3, item 10, lines 104–121: traffic-calming discussion and council consensus for temporary bolt-on speed humps.

  2. Staff reported speed tables installed

    Manager’s project update reports installation and plans for radar signs. This is a staff statement captured in official minutes.

    Source: August 5, 2025 City Council minutes, PDF page 2, lines 75–78: manager reports speed tables installed and radar signs planned.

  3. Manager described positive pilot feedback

    Staff said elements could be applied to South Avenue and a start-date estimate would return later. This is not a measured crash or speed-reduction result.

    Source: August 4, 2026 City Council minutes, PDF page 4, lines 142–145: manager describes positive pilot feedback and proposed South Avenue application.

Key facts

Location
Oak Valley Boulevard
Jurisdiction
City of Minneola
Applicant
Not yet on record
Project acreage
Not yet on record
Funding
Not yet on record

Source: March 4, 2025 City Council minutes, PDF page 3, item 10, lines 104–121: traffic-calming discussion and council consensus for temporary bolt-on speed humps. · August 5, 2025 City Council minutes, PDF page 2, lines 75–78: manager reports speed tables installed and radar signs planned. · August 4, 2026 City Council minutes, PDF page 4, lines 142–145: manager describes positive pilot feedback and proposed South Avenue application.

Original source records

Project evidence: versions & locators (3)

Suggest a correction.

About this data

What these records can establish

Every stage needs its own cited evidence. Undocumented earlier stages remain “Not yet on record”, even when a later stage is documented. Current status requires current evidence.

  • Costs and funding have not been matched to a purchase order or budget line.
  • Measured traffic-safety outcomes remain unverified.
  • The selected minutes do not verify later repaving, full project completion or a future hearing date.